IT House news on July 5th, according to CCTV news reports, Qinghai Zhongkong Delingha 50MW CSP station stated to the public that at 19:18 that day, the power generation capacity of the power station was 755,200 kWh. Since August 5, 2021, The cumulative actual power generation of the power station reached 146 million kWh,It exceeded the annual design power generation (146 million kWh) one month ahead of schedule, becoming the first CSP station in the country whose annual actual power generation completely reached and exceeded the design level.

IT House has learned that the SUPCON Delingha 50 MW tower CSP project is located on the Gobi Desert in Delingha City, Haixi Prefecture, Qinghai Province, covering an area of ​​3.3 square kilometers.

According to the data, Qinghai SUPCON Delingha 50MW CSP station was connected to the grid for power generation on December 30, 2018; from January to June 2019, it mainly carried out shortage elimination and trial operation, and began to enter the regular operation stage in July 2019.

The person in charge of Qinghai Supcon Delingha 50MW CSP plant said that Qinghai Supcon Delingha 50MW CSP plant is one of the first CSP demonstration projects in the country, with an installed capacity of 50MW and a 7-hour molten salt energy storage system. The field lighting area is 542,700 square meters, and the designed annual power generation is 146 million kwh, which can save 46,000 tons of standard coal and reduce carbon dioxide gas by about 121,000 tons each year, which has good economic and social benefits. The power station adopts the tower-type molten salt CSP core technology independently developed by Zhejiang Kesheng Technology Co., Ltd. and fully owns the intellectual property rights. More than 95% of the equipment has been localized. At the same time, the operation performance of the power station has passed the complete technical evaluation of Fichtner, an independent German engineering consulting company, and it is determined that its technology has reached the most advanced level of similar power stations in the world.

Data from the State Grid Qinghai Electric Power Company shows that currently, Qinghai has a total installed power generation capacity of 42.9 million kilowatts. Photovoltaic is the largest power source in the province, accounting for 39.1% of installed capacity, 61.5% of new energy, and 90.8% of clean energy. , the proportion is the first in the country. Among them, the total installed capacity of photovoltaics is 16.77 million kilowatts, the total installed capacity of hydropower is 12.59 million kilowatts, the total installed capacity of wind power is 9.62 million kilowatts, and the total installed capacity of thermal power is 3.93 million kilowatts; both photovoltaic and wind power are new energy, with a total installed capacity of 26.39 million kilowatts; For clean energy, the total installed capacity is 38.98 million kilowatts.

.